Battery construction timeline
Planning: Complete
- Public engagement and site selection
- Develop construction plans, obtain appropriate approvals and permits
- Select vendor and order the battery
- Site clearing completed by Chu Níikwän
Site preparation: Ongoing until winter 2023/24
- Build construction access road to the commercial area (Chu Níikwän)
- Grade the site
- Lay the foundations
Construction: Ongoing until fall 2024
- Build the transmission line connection to the grid
- Install the perimeter fence
- Install the battery components
- Install security and fire-monitoring and fire-suppression systems
- Emergency-responder training
Battery in-service: Winter 2024/2025
- Ongoing operations and maintenance