Battery construction timeline

Planning: Complete

  • Public engagement and site selection
  • Develop construction plans, obtain appropriate approvals and permits
  • Select vendor and order the battery
  • Site clearing completed by Chu Níikwän

Site preparation: Ongoing until winter 2023/24

  • Build construction access road to the commercial area (Chu Níikwän)
  • Grade the site
  • Lay the foundations

Construction: Ongoing until fall 2024

  • Build the transmission line connection to the grid
  • Install the perimeter fence
  • Install the battery components
  • Install security and fire-monitoring and fire-suppression systems
  • Emergency-responder training

Battery in-service: Winter 2024/2025

  • Ongoing operations and maintenance