Tenders and Proposals Registry

Search here for our current requests for services, products and information.

All Yukon Energy public postings can be accessed through Merx at www.merx.com 

Tender #

Description

Close Date

REQUEST FOR EXPRESSION OF INTEREST Wareham Dam Spillway Construction, Mayo, Yukon

YUKON ENERGY CORPORATION is issuing in a Request for Expression of Interest to assess the interest and qualifications of contractors for the construction of proposed additional spillway capacity to an existing dam in Mayo, Yukon and rehabilitation of its existing spillway. 

Documents can be found on Merx here

Nov 28, 2024
RFP 2024-019 Mayo Rock Slope Remediation and Surge Tank Replacement

The Mayo A Hydro site (MH0) was initially commissioned in 1952 and expanded in 1956 to the current configuration of 2 x 2.5MW Francis turbine-generators. In 2012 the Mayo B Hydro station was added to the facility. This new site has two Francis turbines. Mayo A Hydro and Mayo B Hydro are fed from a joint intake in Wareham Lake. The rock slope above the MH0 plant experienced significant rockslides in 2022 and 2023 and has been found to be at risk of future failure. The slope needs to be stabilized to ensure continued safe operation of the plant into the future. There is a surge tank located on the rock slope that provides hydraulic protection to the Mayo Generating Station (MGS). The surge tank is over 70 years old, has been deemed end of life and needs to be replaced.

There are two main Scopes of Work.

1. Stabilizing the slope to prevent future rockslides and slope failure.
2. Replacing the MH0 surge tank along with associated electrical work.

Yukon Energy is combining the slope stabilization and surge tank replacement projects due to the small footprint and steep slope of the site, which make it practical to address both issues simultaneously. The requirement to complete the surge tank replacement in 2025 and the slope stabilization by 2026 necessitates a coordinated approach to prevent delays. Crucially, stabilizing the slope above the surge tank is necessary to ensure safety and structural integrity before constructing the new tank. By executing both scopes of work concurrently, Yukon Energy can
achieve schedule efficiencies, streamlining the overall project timeline. 

A construction sequence to align these two scopes has been developed to minimize risk and meet the Corporation’s needs for generation and water flow.

Proponents are expected to download the solicitation package through the MERX link here.

Dec 13, 2024