Today's question: I heard you on the radio today talking about Mayo B, but what about Aishihik 3? Is it up and running? Are you going to have a press release about that too? That is a good news story too because it was the clean-air funding that paid for that right? Another green milestone for the Yukon. Thanks.
Thanks for that. Yes indeed, our new seven-megawatt hydro turbine at our Aishihik plant is about to go into service. We are just doing the final testing. It should be operating before the end of this year, and we will definitely put out a news release about this project very shortly. Thanks for your interest.