Yukon Energy Terminates Contract with SunGrid Solutions and Announces New Approach to Complete the Whitehorse Battery Storage Project

Nov 23, 2026

Whitehorse, Yukon – Yukon Energy has terminated its contract with SunGrid Solutions (SunGrid) and will assume the role of prime contractor to complete the Whitehorse Grid-Scale Battery Energy Storage System (BESS) Project 

The decision follows SunGrid's failure to achieve substantial completion of the project within the timeframe required under its contract. After carefully assessing the available options, Yukon Energy has exercised its contractual rights and is moving forward with a new approach to complete the project in 2027. 

“Our priority is to get this important project back on track so it can deliver the benefits Yukoners have been waiting for,” said Paul Murchison, Vice President of Capital Projects and Engineering. “We have carefully considered the challenges, the work remaining and the options available to us. We believe this change provides the best path toward completing the project safely and responsibly.” 

Under the new approach, Yukon Energy will serve as the prime contractor, working directly with specialized subcontractors and procuring the equipment needed to complete the project. Hatch, a global engineering firm, will continue to support the project by providing project management services and technical expertise to help coordinate and oversee the remaining work. 

Hatch brings valuable continuity to the project, having been involved in its original design and engineering. The company also has experience supporting battery energy storage projects elsewhere in Canada. 

Work remaining on the battery includes addressing outstanding deficiencies, integrating equipment and systems, and completing the testing and commissioning required before the facility can begin operating. Yukon Energy will also complete an independent review of the project and expects to make the findings public upon its completion in 2027. 

The goal remains to complete the project within its $35 million budget, subject to confirmation of outstanding equipment and subcontractor pricing. Further updates will be provided as Yukon Energy validates the remaining scope, schedule and costs. 

While terminating the contract does not mean Yukon Energy is initiating legal proceedings against SunGrid, Yukon Energy will continue to pursue damages and other remedies available under the contract. 

“We recognize the frustration caused by delays to this project and understand the importance of bringing it into service,” said Murchison. “Our focus now is on working to establish a realistic schedule, complete the remaining work and keep Yukoners informed as the project progresses.” 

Once operational, the BESS will help Yukon Energy meet peak winter electricity demand and strengthen the reliability and resilience of Yukon's electricity system. 

More information about project work completed this summer can be found here.  

Quick Facts: 

  • Current Project Budget: $35 million 

  • SunGrid Contract Value: $25.7 million 

  • Target Completion: 2027  

  • SunGrid was contracted in 2022, following a competitive procurement process. 

  • Hatch is a global engineering, project delivery, and professional services firm. They have been supporting the project since 2020.    

  • In 2019, the Government of Canada committed $16.5 million to the project through the Green Infrastructure Stream of the Investing in Canada Infrastructure Plan. To date, Yukon Energy has received $15 million in contributions. The remaining 10% ($1.65 million) is withheld until project completion. 