News & Events

Check this section for Yukon Energy's latest news and coming events.

If you have questions about any of the information posted here, please contact:


Communications and Community Relations
Phone: (867) 393-5398
Email: communications@yec.yk.ca

Nov 23, 2026

Yukon Energy Terminates Contract with SunGrid Solutions and Announces New Approach to Complete the Whitehorse Battery Storage Project

Whitehorse, Yukon – Yukon Energy has terminated its contract with SunGrid Solutions (SunGrid) and will assume the role of prime contractor to complete the Whitehorse Grid-Scale Battery Energy Storage System (BESS) Project  The decision follows SunGrid's failure to achieve substantial completion of the project within the timeframe required under its contract. After carefully assessing the available options, Yukon Energy has exercised its contractual rights and is moving forward with a new approach to complete the project in 2027.  “Our priority is to get this important project back on track so it can deliver the benefits Yukoners have been waiting for,” said Paul Murchison, Vice President of Capital Projects and Engineering. “We have carefully considered the challenges, the work remaining and the options available to us. We believe this change provides the best path toward completing the project safely and responsibly.”  Under the new approach, Yukon Energy will serve as the prime contractor, working directly with specialized subcontractors and procuring the equipment needed to complete the project. Hatch, a global engineering firm, will continue to support the project by providing project management services and technical expertise to help coordinate and oversee the remaining work.  Hatch brings valuable continuity to the project, having been involved in its original design and engineering. The company also has experience supporting battery energy storage projects elsewhere in Canada.  Work remaining on the battery includes addressing outstanding deficiencies, integrating equipment and systems, and completing the testing and commissioning required before the facility can begin operating. Yukon Energy will also complete an independent review of the project and expects to make the findings public upon its completion in 2027.  The goal remains to complete the project within its $35 million budget, subject to confirmation of outstanding equipment and subcontractor pricing. Further updates will be provided as Yukon Energy validates the remaining scope, schedule and costs.  While terminating the contract does not mean Yukon Energy is initiating legal proceedings against SunGrid, Yukon Energy will continue to pursue damages and other remedies available under the contract.  “We recognize the frustration caused by delays to this project and understand the importance of bringing it into service,” said Murchison. “Our focus now is on working to establish a realistic schedule, complete the remaining work and keep Yukoners informed as the project progresses.”  Once operational, the BESS will help Yukon Energy meet peak winter electricity demand and strengthen the reliability and resilience of Yukon's electricity system.  More information about project work completed this summer can be found here.   Quick Facts:  Current Project Budget: $35 million  SunGrid Contract Value: $25.7 million  Target Completion: 2027   SunGrid was contracted in 2022, following a competitive procurement process.  Hatch is a global engineering, project delivery, and professional services firm. They have been supporting the project since 2020.     In 2019, the Government of Canada committed $16.5 million to the project through the Green Infrastructure Stream of the Investing in Canada Infrastructure Plan. To date, Yukon Energy has received $15 million in contributions. The remaining 10% ($1.65 million) is withheld until project completion. 

Nov 20, 2026

November 2026 Customer Billing Update

Accurate Billing and Customer Support  Providing customers with accurate bills, timely information, and responsive support remains a priority for Yukon Energy. We recognize the importance of getting billing right and ensuring customers have access to the information and assistance they need.  Customers with questions about their accounts or bills, or who may be having trouble paying their bill in full, are encouraged to contact our Customer Service team at billing@yec.yk.ca or (867) 993-5565.   Independent Audit of Customer Billing  The independent audit of electricity customer billing remains underway. The audit was commissioned by ATCO and is being conducted by MNP LLP. Once complete, its findings and recommendations will be made public.  Meter Access and Accurate Billing During Winter  As winter approaches, electricity consumption typically increases, particularly in homes and businesses that rely on electric heating. Seasonal changes in energy use can have a noticeable impact on electricity bills, making accurate meter readings and clear billing information especially important.  Safe access to meters is also essential during the winter months. Most customers receive bills based on actual meter readings. However, when snow, ice or other hazards prevent safe access to a meter, an estimated bill may be issued until an actual reading can be obtained.  Customers can help support accurate billing and effective communication by taking a few simple steps:  Keep meters accessible. Clear snow and ice from access routes and ensure meter locations can be reached safely by meter readers.  Keep account information up to date. Let us know if your contact information changes so we can reach you when necessary.  Plan for seasonal electricity costs. Winter heating demand can significantly affect electricity consumption. Consider seasonal changes when planning your household or business energy budget.  Look for opportunities to conserve energy. Use timers for thermostats and block heaters, limit the use of space heaters where possible, and consider other practical ways to manage electricity consumption.  Peak Smart   You can help support the Yukon's electricity system by signing up for Peak Smart Home. The Peak Smart Home program helps shift electricity use away from periods of high demand, particularly during cold winter mornings and evenings when demand is highest.  By enrolling eligible smart thermostats or hot water tank controllers, you can help reduce pressure on the electricity grid when it matters most.   If you are interested in participating in the Peak Smart Home program, visit peaksmart.ca to learn more, check eligibility and sign up.   Continuing to Improve  As we move into the winter season, we remain focused on delivering accurate bills, responsive customer service, and clear communication.  Customers can expect us to:  Provide clear and accurate billing information.  Investigate billing concerns thoroughly and fairly.  Respond to inquiries as quickly as possible.  Communicate openly when issues are identified.  Continue improving our billing and customer service processes.  We will continue to share updates as improvements are implemented and progress is made.    You can read our October update here.  

General, News
Nov 13, 2026

Federal Budget Recognizes Three Major Yukon Energy Projects

Federal Budget Recognizes Three Major Yukon Energy Projects November 13, 2026 Yukon Energy welcomes the Government of Canada's recognition of three major electricity projects in Budget 2026 that will help strengthen the reliability of Yukon's electricity system, support growing communities and meet the territory's increasing demand for power.  Tabled on November 5, 2026, Budget 2026 identifies three important Yukon electricity projects for federal funding: upgrades to the Mayo Hydro Facility, the Whitehorse Power Centres and the Atlin Hydro Expansion Project, being developed by the Taku River Tlingit First Nation's development corporation.  While the specific funding amounts, timelines and details for each project have not yet been confirmed, their inclusion in the federal budget is an encouraging step forward. Yukon Energy looks forward to working with the Governments of Yukon and Canada to better understand the proposed investments and next steps.  These projects are important to Yukon's energy future. Upgrades to the Mayo Hydro Facility are needed to modernize aging infrastructure, address critical dam safety risks and ensure the facility can continue to operate safely and reliably for decades to come. The Whitehorse Power Centres will provide the dependable generating capacity needed to meet growing winter electricity demands and reduce the risk of power outages. The Atlin Hydro Expansion Project will bring additional sources of renewable electricity we can rely on during the winter, helping reduce reliance on diesel and LNG generation.  Grant funding from governments is essential to advancing these projects while keeping electricity affordable for Yukoners. The Mayo Hydro upgrades and Whitehorse Power Centres alone represent approximately $1 billion in planned investments. Without significant grant funding from both the Governments of Yukon and Canada, these costs would place additional pressure on electricity rates. Every dollar secured through federal and territorial grants helps reduce the amount that would otherwise need to be recovered from Yukoners through their electricity bills.  Yukon Energy appreciates the ongoing collaboration and advocacy of the Government of Yukon and Yukon Development Corporation in advancing these priorities and welcomes the recognition of the importance of reliable electricity infrastructure in the North.  These projects are central to building a stronger, safer and more reliable electricity system that can support Yukon's communities and economy for decades to come. 

General, News, Billing
Oct 21, 2026

October 2026 Customer Billing Update

Independent Audit of Customer Billing  The independent audit of electricity customer billing remains underway. The audit was commissioned by ATCO and is being conducted by MNP LLP, an external firm that selects the customer accounts to be tested, carries out the review, and will issue its findings under its own name. The review is examining:  All accounts at a macro level to understand whether the system calculated and charged the right amount for power.  A sample of accounts throughout the Yukon to understand whether individual bills were calculated accurately, in line with approved rates and terms of service.  The findings will be made public once the review is complete. We will continue to provide updates as the work progresses and use the results to help inform ongoing efforts to improve billing accuracy and reliability.  Meter Reads and Customer Support  Most customers receive bills based on actual meter readings. Estimates may still be necessary when a meter cannot be accessed to obtain a reading. In these situations, customers receive a bill based on an estimated amount of electricity use.   We continue to work on improving how the billing system calculates estimates and to respond to customer concerns related to estimated bills and billing adjustments needed the next time an actual meter read is collected.  We recognize that a higher-than-expected bill can be stressful. We have added another staff member to strengthen our Customer Service team and help improve response times. Our goal is to ensure bills are accurate and timely, and that customer questions and concerns are investigated and addressed as quickly as possible.  If you have questions about your account or bill, or concerns about being able to pay your bill in full, please get in touch with our Customer Service team at billing@yec.yk.ca or (867) 993-5565.  If you reach our voicemail, please leave a detailed message with your contact information and the reason for your call. Voicemails are added to our callback list and returned in the order they are received.  What Customers Can Do?  As we move into another winter, there are several ways customers can help support accurate billing and avoid unexpected adjustments wherever possible.   Make your meter accessible. Keep access routes clear. This helps our meter reader safely obtain an actual reading whenever possible.  Keep your account information current. Advise us when your contact details change so we can reach you when needed.  Plan for seasonal electricity use. Electricity consumption can change considerably during the winter, particularly when heating demand increases. Keep seasonal changes in mind when planning for your electricity costs.  Look for ways to conserve energy. Use timers for thermostats and block heaters to help manage electricity use. Limit the use of space heaters where possible and consider other ways to reduce energy consumption during the winter months.  Have questions about your bill? Contact Yukon Energy or ATCO Electric Yukon, depending on your electricity provider.  Rebuilding confidence  We know that rebuilding confidence takes consistent action, clear communication, and accountability. We remain focused on addressing the underlying issues contributing to billing challenges and resolving individual issues as they arise.  Last week, Yukon Energy staff visited Dawson City to provide customers with in-person billing support. We continue to visit the communities we directly serve on a rotating basis to ensure customers have access to in-person assistance when needed.  We will continue to provide regular updates as we address billing system issues, improve billing processes, and work toward a more accurate, timely and reliable billing experience for customers.   You can read our September update here.  

Oct 02, 2026

Update on the Whitehorse Grid-Scale BESS Project - Fall 2026

Yukon Energy understands that delays to the Whitehorse Grid-Scale Battery Energy Storage (BESS) Project have been frustrating and disappointing. We share that frustration and remain committed to completing this important project and bringing the benefits of grid-scale battery storage to the Yukon’s electricity system.  When operational, the battery will help strengthen the reliability and resilience of the Yukon’s electricity system, providing an additional source of dependable winter capacity and providing firm back-up for current levels of solar and wind power.  The project is being delivered by SunGrid, an external contractor, who recently advised us of a further change to the project schedule. Earlier this spring, SunGrid provided a schedule showing the project could be completed this summer. We were hopeful that the timeline could be met; however, those dates were not achieved.  The continued delays do not meet SunGrid’s commitments to Yukon Energy. Yukon Energy is enforcing the contract, including financial penalties for missed deadlines, while also meeting regularly with SunGrid to ensure the project advances.  Despite the delays, work has continued and there has been progress at the site this summer, including:  Power is now available at the site to support the battery equipment and the testing needed before the facility can begin operating.  Insulating gravel has been installed around the site as an important safety measure.  LG Energy Solution, the battery manufacturer, has been on site preparing and testing the batteries. This work is ongoing.  We have heard concerns raised in the community about battery life and reliability. During an extended period of cold weather last winter, SunGrid’s temporary power source, which supplied heat to the battery containers, failed and exposed the batteries to extremely low temperatures. Although this does not necessarily mean the batteries were damaged, extreme cold can affect their performance. LG Energy Solution’s test results will help determine whether—and to what extent—last winter’s conditions affected the batteries.   Before the battery system is placed into service, the new technology will undergo extensive testing to ensure it operates safely and reliably. We will not rely on the system to meet electricity demand this winter. In the meantime, we have added other sources of supply to the grid since last winter, including two new diesel generators at our existing Whitehorse facility.  This battery project has provided important lessons that Yukon Energy can apply to future projects involving new technologies. As the battery system nears completion, we will undertake a review of these lessons learned. This review will help strengthen the planning, procurement, and delivery of future capital projects.  Yukoners have long been leaders in renewable electricity, and we know there is excitement about bringing this new technology to the North. We appreciate Yukoners’ continued patience as we work to ensure the battery is safely and reliably integrated into our electricity system.  We will continue to provide updates as the project moves forward. 

Sep 25, 2026

Whitehorse Diesel Noise Mitigation Update - Fall 2026

As we prepare for this upcoming winter, we wanted to provide an update on the noise mitigation solution we are working to implement at the Whitehorse Rapids Diesel Facility.  Our plan is to replace the exhaust silencers on the facility’s four older diesel units with newer, more effective equipment. These older units have been found to be louder than the diesel engines we rent in the winter and the newer engines. Yukon Energy began the procurement process for the work in April 2026 and selected a contractor in July 2026. Design work is now underway.  While we had hoped for these silencers to be installed before this winter season, the contractor has advised that manufacturing the new silencers will take longer than we had originally anticipated due to high demand for electricity infrastructure and equipment across North America. Installing the silencers also requires taking the diesel units out of service for an extended period. Our diesel units provide important backup power during the winter and need to remain available in case they are required to support the grid. As such, we are planning to install the new silencers in summer 2027, after the peak winter period, when electricity demand is lower, and the work can be completed with less risk to the reliability of the power system. We recognize this timeline extends beyond that in our Whitehorse air emissions permit. We have let our regulator, Environment Yukon, know of reasons for the delay and will keep them updated on our progress.  In the meantime, we have installed two new diesel generators at our Whitehorse facility as part of the thermal replacement project. These generators are expected to be available this winter, which should help reduce how often we need to use the older, louder diesel units. The new generators use newer, quieter technology and are located such that they have some shielding from the building that houses the older units, both of which will help to reduce noise heard by Riverdale residents. 

Sep 21, 2026

September 2026 Customer Billing Update

ATCO Billing Audit for Yukoners  ATCO Electric Yukon has launched an independent third-party review of the electricity billing system used to generate electricity bills for both ATCO Electric Yukon and Yukon Energy customers. The review is being conducted by MNP LLP, an independent firm with expertise in utility billing systems, business processes, and customer service.   The purpose of the review is to confirm that customers are being billed accurately and to identify opportunities for improvement with the billing system. The audit will review a sample of customer accounts across both utilities to assess the accuracy of billing across the system and identify opportunities for improvement. This is a system-wide audit and is not intended to provide customers with a detailed review or determination of whether their individual account has been billed correctly. ATCO will absorb all costs of the review.  Yukon Energy customers who would like their account to be considered for inclusion in the audit can register by completing the online Opt-In Form by September 25, 2026. Register here: www.atcoelectricyukon.com/audit  The final customer sample and participant selection criteria will be determined solely by MNP LLP based on audit parameters and methodology. Neither ATCO Electric Yukon nor Yukon Energy will influence the selection of participants.  Meter Reading and Billing Accuracy   We continue to collect meter readings from homes and businesses across Yukon to ensure bills accurately reflect electricity usage.   When an actual meter read cannot be collected — for example, when a meter is blocked or inaccessible — we contact the customer directly by door hanger, email or phone to let them know.   Our Customer Service Representatives also continue to manually review every bill for accuracy before it is issued. Less than 1% of bills have required corrective action, and 99% of bills have been issued on time. When specific issues are identified, such as billing adjustments, refunds, or payment arrangement needs, affected customers are contacted directly by our Customer Service Representatives and supported through the resolution process.   Addressing System Issues and Root Causes   Yukon Energy continues to work closely with ATCO Electric Yukon and our billing system provider to investigate known system issues, address their root causes and implement both interim corrective measures and longer-term solutions.   This work is making progress on several issues that directly affect customers, including:  Improve the logic used to calculate estimated bills when an actual meter read cannot be obtained. The goal is to ensure estimates better reflect seasonal changes in electricity use and are more accurate;  Adjust system thresholds to allow more actual meter readings to be accepted and used for billing when it is significantly higher or lower than previous months; and  Streamline the number and type of system flags generated each day that require review before bills can be issued. This helps bills reach customers more quickly.    Senior leaders from both utilities also continue to meet regularly to oversee progress. Yukon Energy has also onboarded a new Customer Service Representative to help provide additional customer support. This added capacity will help the team respond more quickly and effectively to customer requests.  Support for Customers  If you have questions about your account or bill, or concerns about being able to pay your bill in full, please get in touch with our Customer Service team at billing@yec.yk.ca or (867) 993-5565.  Every inquiry is reviewed individually, and we remain committed to working directly with customers to understand and resolve their concerns.  We will continue to provide regular updates as we address billing system issues, improve billing processes, and work toward a more accurate, timely and reliable billing experience for customers.   You can read our August update here. 

Sep 03, 2026

Yukon Energy announces final two proposed sites for Whitehorse Power Centres Project

WHITEHORSE, Yukon – Yukon Energy has identified two final proposed sites for the Whitehorse Power Centres Project, a key initiative that is needed to meet winter demand for power, as well as support growth and the integration of more community renewables in the Yukon. The project will be assessed through the Yukon Environmental Socio-economic Assessment Board (YESAB) for up to 150 MW, essentially doubling the size of the Yukon’s electricity system.   The selected sites are:  North: Ta’an Kwäch’än Council (TKC) Deep Creek  South: Copper Haul Road  Located on TKC Settlement Land, the Deep Creek site reflects years of collaboration between Yukon Energy and Ta’an Kwäch’än Council to identify a suitable location that balances reliable electricity with environmental, community and cultural considerations.  As the project advances, Yukon Energy will continue working with both the Ta’an Kwäch’än Council and Kwanlin Dün First Nation. This includes ongoing collaboration on project planning and development, as well as exploring opportunities for investment, procurement, contracting and broader economic participation across the Whitehorse Power Centres Project.  The final proposed site selections were informed by extensive technical studies and community engagement with Ta’an Kwäch’än Council, Kwanlin Dün First Nation, the Yukon government, the City of Whitehorse, other stakeholders and the public Ta’an Kwäch’än Council also conducted its own engagement with Citizens before the final site selection.  Along with community feedback, project cost, technical feasibility, operational requirements and permitting considerations were key factors in selecting the final locations.  With the sites now confirmed, Yukon Energy will continue advancing project planning and engineering. This work includes refining site layouts and power centre design, as well as completing the environmental and technical studies required to support a regulatory review.  Yukon Energy will also be evaluating both liquefied natural gas (LNG) and diesel as potential fuel options for the project. The decision to include both fuel types in the upcoming project proposal to the YESAB reflects additional information and feedback received during the YESAB Pre-Submission Engagement process, such as concerns regarding emissions, noise and fuel security.  Planning is also continuing for the transmission lines needed to connect both sites to the Yukon grid. Where practical, new powerlines will follow existing transmission corridors or road rights-of-way to reduce environmental and community impacts. Yukon Energy will continue engaging directly with property owners along the proposed routes as this work progresses. A map of the transmission line routes is available here.  Yukon Energy plans to submit the full Whitehorse Power Centres project proposal to YESAB this fall. The submission will include additional information on project design, environmental mitigation measures and the assessment of both fuel options.  At the same time, Yukon Energy will continue working through City of Whitehorse planning processes related to the Copper Haul Road site.  Quotes  “Building the electricity system that Yukoners can rely on today and into the future takes strong partnerships. It requires utilities, First Nations and other governments, and businesses working together toward a common goal. We look forward to continuing our work with Ta’an Kwäch’än Council, Kwanlin Dün First Nation and the Government of Yukon as we advance the Whitehorse Power Centres Project and create meaningful opportunities that support a reliable and resilient energy future for all Yukoners."  Yukon Energy President and CEO Joe MacGillivray  "Ta’an Kwäch’än Council has carefully reviewed the proposed Deep Creek site through community engagement, our Elders Council and our General Assembly. Having reached community approval allows this site to be considered as a potential location. We are pleased to move forward with Yukon Energy into the next stages of environmental, technical and regulatory assessment.  As landowners in an urban community experiencing unprecedented growth, we recognize the importance of expanding reliable energy infrastructure to support our region’s future. At the same time, development must respect our lands, culture, and community priorities. We look forward to the discussions and negotiations ahead and to working with Yukon Energy to identify opportunities that create meaningful and lasting benefits for our Citizens and community.”   Ta’an Kwäch’än Council Chief Ruth Massie  Media Inquiries:  Yukon Energy  Keely Bass, Project Communications Lead  Keely.bass@yec.yk.ca  867-332-1854  Ta’an Kwäch’än Council  Janet Smellie, Communications Officer  communicationsoffice@taan.ca   (867) 668-3613 ext. 204  Cell: (867) 334-5298 

Aug 19, 2026

August 2026 Customer Billing Update

Yukon Energy and ATCO Electric Yukon continue to provide monthly public updates on the work underway to address customer billing concerns related to estimated bills, account calculations, payment processing and billing timing.  We understand these issues have caused frustration and uncertainty for many Yukoners. We remain committed to providing accurate, timely and easy-to-understand bills while addressing individual customer concerns and the underlying system issues that have contributed to billing problems.  Meter Reading and Billing Accuracy  We continue to collect meter readings from homes and businesses across Yukon to ensure bills accurately reflect electricity usage.  When an actual meter read cannot be collected — for example, when a meter is blocked or inaccessible — we contact the customer directly by door hanger, email or phone to let them know.  Our Customer Service Representatives also continue to manually review every bill for accuracy before it is issued. Less than 3% of bills have required corrective action, and 99% of bills have been issued on time. When specific issues are identified, such as billing adjustments, refunds, or payment arrangement needs, affected customers are contacted directly by our Customer Service Representatives and supported through the resolution process.  Addressing System Issues and Root Causes  Yukon Energy continues to work closely with ATCO Electric Yukon and our billing system provider to investigate known system issues, address their root causes and implement both interim corrective measures and longer-term solutions.  This work is making progress on several issues that directly affect customers, including:  Improving estimated bills: We are reviewing the logic used to calculate estimated bills when an actual meter read cannot be obtained. The goal is to ensure estimates better reflect seasonal changes in electricity use. This should result in more accurate estimates, smaller adjustments when the next actual meter read is collected, and less potential for unexpected high bills.  Increasing the use of actual meter reads: We are reviewing and adjusting system thresholds to allow more actual meter readings to be accepted and used for billing when it is significantly higher or lower than previous months. Our review has found that the current thresholds do not adequately account for the large seasonal changes in electricity use that can occur in the Yukon. Adjusting them should allow more bills to be based on actual meter reads rather than estimates.  Streamlining account review and controls: We are working to streamline the number and type of system flags generated each day that require review before bills can be issued. This will allow our team to focus more time on genuine billing anomalies and help bills reach customers more quickly.  Additional work is underway to review billing processes, system parameters, billing timelines and how information is displayed on customer bills — all with the goal of improving reliability, accuracy and clarity.  Leadership Oversight Driving Progress   Senior leaders from ATCO Electric Yukon, Yukon Energy, and ATCO meet every two weeks to review progress on billing improvements, remove barriers, and ensure the work remains a top priority. These regular meetings help maintain accountability, monitor customer impacts, and confirm the teams have the resources and support needed to implement both immediate fixes and long-term solutions  Responding to Customer Inquiries  Yukon Energy is adding a new Customer Service Representative to our team this month. This additional resource will help reduce wait times during periods of higher demand, provide more timely support to customers with billing questions, and give the broader team additional capacity to resolve billing issues and advance system improvements.  We recently visited Faro to meet directly with customers in the community, review bills and answer questions. Community visits like this are an important part of our efforts to better understand customers' experiences and provide hands-on support.  Non-Billing Service Fees  In January, the Yukon Utilities Board approved updated Terms and Conditions of Service, utility contributions for new customer connections, and fees for non-billing services such as connection and disconnection requests.  While new utility contribution levels approved by the Yukon Utilities Board are in effect, implementation of updated non-billing service fees remains on hold as we continue to focus on billing improvements. Customers will continue to be charged the lower fee levels established in 2011 for services such as connections, disconnections, and after-hours call-outs until further notice.  Support for Customers  If you have questions about your account or bill, please contact our Customer Service team at billing@yec.yk.ca or (867) 993-5565.  Every inquiry is reviewed individually, and we remain committed to working directly with customers to understand and resolve their concerns.  We will continue to provide regular updates as we address billing system issues, improve billing processes and work toward a more accurate, timely and reliable billing experience for customers.   You can read our July update here. 

News
Aug 03, 2026

Yukon Energy takes the next step toward long-term relicensing of Aishihik Hydro Facility

Yukon Energy has submitted a project proposal to the Yukon Environmental and Socio-economic Assessment Board (YESAB), marking the start of the environmental and socio-economic assessment process for the long-term relicensing of the Aishihik Hydro Facility.  The Aishihik Hydro Facility is one of Yukon's most important hydroelectric generating facilities and a critical source of renewable electricity during the winter months. It is the territory's only hydro facility with multi-year water storage capacity, providing reliable, flexible generation that helps meet the Yukon's electricity needs year-round.  The submission builds on the Äshèyi Agreements signed in 2022 by Yukon Energy, the Champagne and Aishihik First Nations (CAFN), and the Government of Yukon. The agreements established a collaborative framework and renewed relationship for working together on the future of the facility, including participation in assessment and licensing processes, territorial energy planning and production, and the monitoring and stewardship of Äshèyi.  This submission represents an important milestone in that shared commitment. Over the past several years, Yukon Energy, CAFN and the Government of Yukon have worked together to prepare for the assessment and relicensing process. The goal is to secure long-term authorization for the facility while supporting reliable, renewable electricity for Yukoners, advancing reconciliation, and respecting CAFN's cultural practices and enduring connection to Äshèyi.  Additional information about the project will be available through the YESAB Online Registry as the assessment process progresses.