In 2025, Yukon Energy received an air emissions permit to operate diesel generators at our substation in Callison near Dawson City.
Initially, we have installed 6.5 megawatts of diesel generation at the facility. In future years, we expect more diesel generation at the substation as demand for power in Dawson City continues to grow, more sources of wind and solar power come online, and we continue to move diesel generators from downtown to Callison. To prepare for that, we assessed the potential long-term effects of 15.5 megawatts of diesel generation at the Callison substation.
More information about the project is available here.