About Us

News
Jul 16, 2012  Comment

The Latest on Our Biomass Work

There's some good news on the biomass front. We are working with four local governments, agencies and corporations to look into the possibility of a biomass project for Haines Junction. The Champagne and Aishihik First Nations, the Dakwakada Development Corporation, Cold Climate Innovation of the Yukon Research Centre, and the Village of Haines Junction are collaborating with us to investigate the potential for a two to three megawatt biomass plant in the community. If approved, the plant would provide some much-needed renewable electricity for the territory. It also has the potential to produce district heat and create economic opportunities for local businesses and corporations. The preliminary research done to date shows this is a potentially economically viable project. As a group we are now hiring a consulting company to conduct a more detailed engineering and design study. The results are expected by early next year. While this study will primarily focus on electricity production from the plant, the group hopes to find additional money to investigate the use of the facility’s waste heat. The bulk of the funding for the $850,000 engineering and design study is expected to come from Natural Resources Canada, with the remainder coming from the five Yukon organizations. Once the study results are known, we will decide as a group how best to move forward. The biomass project would undergo community, environmental and regulatory review before moving to the construction phase.

Energy Supply, Environment
Jul 24, 2012  Comment

Our Latest Summer Forecast for Marsh Lake

While property owners and residents in the Southern Lakes continue to watch the water rise around their homes, we too are keeping a close eye on the levels. Our latest forecast for peak levels on Marsh Lake shows a range. The darker dotted line shows the 'worst case' scenario, with levels reaching 40 cm (16 inches) below 2007 peak levels. The lighter dotted line shows the 'best case' scenario, with levels below the 2004 peak. We continue to get questions about why we are keeping water levels so high this year. In fact we have no ability to control the lake levels at this time of year. Here are a few points that we hope will explain how we are allowed to operate. 1. Today's lake level (July 24) is 656.368 metres above sea level. That is about 16 cm higher that our current Full Supply Level in our water licence, which is 656.23 metres. 2. Our water licence says that we must have all our gates open by May 15th each year, and the gates must remain open until at least August 15th. Even then, we can only close them if the water has dropped to below our Full Supply Level (FSL). That means there are some years when we don't actually start to close gates until late September (typically that happens in higher-than-normal water years such as this one). It also means that during the summer, Yukon Energy does not have the ability to control lake levels. The level you see now is the natural level. 3. Marsh Lake goes to our Full Supply Level elevation naturally every year, and often it goes well above this level. 4. Lake levels today appear to be typical of other high water years. High water years occur about 25 percent of the time. We are also asked what will happen with lake levels if we get permission to go to a new Full Supply Level, as we are looking at in the Southern Lakes Enhanced Storage Concept. 1. The new Full Supply Level that we are considering is 656.53 metres, which is 30 cm (1 foot) higher than the current Full Supply Level. 2. The flood level is 656.79, which is the 2004 water level. That is .26 of a metre (26 cm or close to a foot) HIGHER than the proposed Full Supply Level. "Flood level" is a bit of an arbitrary term, but essentially it's a level where people start to experience some flooding issues. 3. In 2007 Marsh Lake peaked at 657.34. That is .81 of a metre (81 cm) above the proposed Full Supply Level and is more than a metre above today's lake level. 4. Marsh Lake reaches 656.53 (the proposed new FSL) naturally one out of every three to four years. In the last 26 years, the lake has reached this level naturally 10 times: in 2009, 2007, 2004, 2000, 1994, 1993, 1992, 1989, and 1986. 5. Today the lake is approximately 13 cm below the proposed new Full Supply Level. We know this can be a complicated subject, so please don't hesitate to send us a note if you have questions or comments.

Media Releases
Jul 25, 2012  Comment

Yukon Energy Seeks Input on 20-Year Resource Plan

After extensive consultation and discussion with governments, stakeholders and the public, Yukon Energy has completed a draft of its updated 20-year resource plan. It is now taking the draft to Yukoners for input. Then the document will be revised based on feedback from the public and will be submitted to the Yukon Utilities Board (YUB). “In 2006, the last time Yukon Energy developed a 20-year resource plan, our approach with regard to public consultation was fairly conventional. We shared the plan with the public, but only once it was a finished document that had been filed with the YUB,” Yukon Energy president David Morrison said. “Since that time, we have made a conscious and fundamental change in our approach to planning. We sought input from First Nation and other governments, stakeholders and the public before we had determined any of the content of this latest resource plan,” Morrison added. The input came through meetings, workshops, a three-day energy planning charrette held in March 2011, and follow-up mini-charrettes that focused on specific potential energy options. Among other things, the charrette participants helped Yukon Energy formulate four principles around which to base future energy decisions: reliability, affordability, flexibility and environmental responsibility. “These these four principles became our lens through which we considered all possible energy options for this resource plan draft,” Morrison said. The document outlines both near-term and longer-term energy options. Near-term possibilities include energy conservation/efficiencies, hydro enhancements such as Southern Lakes Enhanced Winter Storage, liquefied natural gas, wood biomass, and wind. Longer-term options outlined in the draft include new hydro, geothermal, solar, liquefied natural gas from local sources, and a grid connection to British Columbia or Alaska. Yukon Energy plans to visit several Yukon communities over the next few weeks to hear people’s views on the draft document. On a go-forward basis Yukon Energy is committed to the idea of ‘planning in public’. The corporation will continue engaging Yukoners on issues related to the territory’s energy future. To learn more you are invited to read a summary of the 20-Year Resource Plan draft and a more comprehensive and detailed overview of the plan. The complete document is available upon request (note that it is a very large file).  Contact: Janet Patterson Supervisor, Communications Yukon Energy Corporation (867) 393-5333 janet.patterson@yec.yk.ca