Site planning: Complete
- Preliminary engineering
- Environmental assessments
- Community and stakeholder engagement
- Submission of our Yukon Environmental and Socio-economic Assessment Act proposal
- Procuring equipment with long lead times
Site preparation: Complete
- Survey the site and remove vegetation
- Level the site and complete grading
- Install temporary fencing and signage
- Install foundations for new substation equipment and taller poles
- Install the concrete oil containments needed for the transformer
Construction: Present to August 2023
- Electrical equipment installed in the substation
- Transmission line wire and poles replaced with upgraded structures and wire
NOISE: During construction, you can expect to hear noise typical of a construction site, but we’ll make sure our work abides by all noise bylaws.
Interconnection: Winter 2023/2024
- New equipment in the substation and the upgraded transmission line energized
Ongoing
- Operations and maintenance