News & Events

Check this section for Yukon Energy's latest news and coming events.

If you have questions about any of the information posted here, please contact:

Lisa Wiklund
Manager, Community Relations
Yukon Energy Corporation
Phone: (867) 393-5398
Email: Lisa.Wiklund@yec.yk.ca

Media Releases
Feb 07, 2005  Comment

Big Changes at Yukon Energy Address Mayo/Dawson Transmission Line Audit

(Whitehorse) - The Office of the Auditor General has released its long awaited report on the Mayo/Dawson transmission line project. The report, which was released earlier today, identifies a number of problems encountered by Yukon Energy in constructing the line. While Yukon Energy agrees with the Auditor General’s conclusions that there were numerous difficulties with the project, the company’s president says steps have already been taken to address those issues.   “Yukon Energy recognized some time ago that we needed to make improvements in some areas,” David Morrison said. “That’s in part why we recently changed our capital project processes. A committee now reviews all capital project plans and makes recommendations to the board of directors for approval. Projects have detailed descriptions of scope and forecasted costs.” Yukon Energy has also developed new contracting policies and guidelines that have been approved by the board of directors. Yukon Energy’s forecasts show that the Mayo/Dawson line remains a good project for Yukon ratepayers, saving them about $20 million dollars over the life of the line. Morrison says the company has learned from its past inexperience. “The Mayo/Dawson line was the first major capital project undertaken by Yukon Energy. While the findings in the report certainly demonstrate Yukon Energy did not have the appropriate internal processes to deal with such a large initiative at that time, the measures we have already undertaken and those we plan to carry out shortly will ensure that the problems encountered with the Mayo/Dawson project will not occur in future.” In terms of future plans, Yukon Energy will arrange to have an independent audit done later this year of project management practices and procedures. A project management policy will then be prepared. As well, Yukon Energy is proposing that all projects worth more than $3 million receive prior approval by the Yukon Utilities Board. It was shortly after Morrison became Chair of Yukon Energy in May 2003 that the Corporation’s board of directors requested an audit be done of the Mayo/Dawson project because of concerns about cost over runs and construction delays. “Given the magnitude and significance of the transmission line to the Yukon, the board felt it prudent and responsible to conduct a thorough review of the project,” Morrison said.  A detailed review of the Mayo-Dawson project’s impact on ratepayers is part of public hearings set to occur this spring before the Yukon Utilities Board. Information filed for that hearing shows that the project will result in savings to ratepayers, and that the “break-even” cost for the line is about $52 to $56 million. Construction of the 232 kilometre line from the Mayo hydro generating station to DawsonCity started June 2001 and the line was commissioned in September 2003.  The final price tag for the project is currently estimated at approximately $36 million. -30-  Contact:Janet PattersonCommunications SupervisorYukon Energy Corporation(867) 393-5333                                                           janet.patterson@yec.yk.ca                    

Media Releases
Mar 02, 2005  Comment

Yukon Energy Becomes Member of the ‘Passport to Safety’ Program

(Whitehorse) - Yukon Energy has become part of a national program aimed at eliminating workplace injuries and deaths among young Canadians. The Passport to Safety Program supports and encourages education, knowledge and workplace-specific safety training for young people. It offers an on-line test to help make teenagers and young adults aware of their rights and responsibilities regarding health and safety, and therefore better prepares them to keep safe while at work. “Safety is one of Yukon Energy’s core values,” Yukon Energy’s Manager of Operations, Health and Safety Les Boisvert said. “It’s something we think about every day. We’re pleased to be a recognized Passport to Safety employer and to support the protection of young workers in the territory.” Yukon Energy will promote this program during the hiring process, and completion of the on-line test will be an asset to young people applying for a job at the electrical company. Apart from the on-line training through the Passport to Safety Program, Yukon Energy provides additional safety training to its new employees. Yukon Energy typically hires two or three summer students each year. To find out more about the program, go to www.PassporttoSafety.com.  -30- Contact:Janet Patterson                                                             Supervisor, CommunicationsYukon Energy Corporation(867) 393-5333                                                             janet.patterson@yec.yk.ca  

Media Releases
Apr 01, 2005  Comment

Yukon Government Extends Rate Stabilization Program

(Whitehorse) - The Yukon government is extending the current Rate Stabilization Fund (RSF) on an interim basis for two years. That means the government will continue to provide an electrical subsidy for businesses and residences during this time."Over the two-year period, the Department of Energy, Mines and Resources and the Yukon Development Corp. will undertake a review of the RSF program," Energy, Mines and Resources Minister Archie Lang said.  "They will make long-term recommendations about the future of this program prior to its expiration on March 31, 2007."While working to address a longer-term solution, the government recognizes the importance to consumers of knowing what their power costs will be over the next few years. Without the extension, the amount that consumers pay for residential electricity would increase April 1 by up to 33 per cent, and commercial and municipal bills would increase by up to 11 per cent."We also recognize that energy efficiency is an effective tool that can contribute to an overarching goal of reducing electrical consumption," Lang added. "This extension gives us time to consider new programs that could enhance energy efficiency and the role of the Yukon Utilities Board."The Yukon Development Corporation (YDC) will provide up to $9 million in funding to support the RSF program from April 1, 2005 to March 31, 2007.The Rate Stabilization Fund was established in 1998 after the Faro mine closed, to protect customers from substantial electrical rate increases.The Rate Stabilization Fund subsidizes customer bills so that consumption of the first 1000kWh for residential and 2000kWh for commercial and municipal customers is maintained at nine per cent above rates established in January 1997. - 30 -  Contact:      Peter Carr  Laurie Sthamann  Janet Patterson  Cabinet Communications  Energy, Mines & Resources  Yukon Development Corp.  (867) 667-8766  (867) 667- 3163  (867) 393-5333  peter.carr@gov.yk.ca  laurie.sthamann@gov.yk.ca  janet.patterson@yec.yk.ca       

Media Releases
Jun 03, 2005  Comment

New Initiatives at the Whitehorse Fishladder Focus on Kids

One of the Yukon’s most popular tourist attractions has opened for another season, with some new initiatives aimed at children and families. The Whitehorse Rapids Fishway opened its doors to the public yesterday. “The fishladder has always been a big hit with the kids,” said Fishway Manager Erin Spiewak. “This year we’re adding some programming that we think will make this facility even more enjoyable and educational.” Children will be invited to play games that will enhance their understanding of the cycle of the chinook salmon. As well, both children and adults will have a chance to take part in a contest to guess the arrival date of the first salmon of the season. Starting next month, the Yukon government’s Department of the Environment will offer weekly talks with local experts, on everything from the biology of the salmon to how to fly fish. “We’re also inviting both kids and adults to submit a new design for a fishway T-shirt. There’ll be a prize for the winning entry and the T-shirts will go on sale starting next year,” Spiewak said. Visitors to the fishladder will still be able to enjoy the things they’ve come to expect at the fishladder. There are four underwater cameras that allow people to view fish from different locations along the ladder. Aquariums inside the viewing facility contain a variety of fresh water fish including rainbow trout and arctic char. There’ll be elders’ talks and display materials that focus on traditional First Nations’ use of the Whitehorse portion of the Yukon River. Improvements planned for later this summer include new interpretive signage and brochures which tell the story of the chinook salmon and explain the role that the fishladder and the near-by fish hatchery play in maintaining the salmon stocks. The fishladder was built following the construction of the Whitehorse dam in 1959 to allow migrating Chinook salmon and other species to pass by the structure. It’s owned by Yukon Energy and operated by the Yukon Fish and Game Association. The facility is one of the principal tourism attractions in Yukon, drawing approximately 30,000 visitors annually. -30- Contact:Janet PattersonCommunications, Yukon Energy Corporation(867) 393-5333janet.patterson@yec.yk.ca

Media Releases
Jun 03, 2005  Comment

Local Students Benefit from Yukon Energy Scholarships

This year, Yukon Energy will again award several scholarships to Yukoners studying at post-secondary institutions. “These awards were started a number of years ago, as a way of showing our commitment to the people and the communities we serve,” Yukon Energy spokesperson Janet Patterson said. “There are a lot of bright young minds in the territory, and if we’re lucky they may choose to return to the Yukon to work after their studies are finished.” There are three categories of awards. In the general category, two students will receive $4000 each over two years. To be eligible, students must be studying full-time at a post-secondary school in Canada or Alaska for a diploma or undergraduate degree. They must be pursuing studies in the natural sciences, engineering, technologies, business administration, commerce or economics. This scholarship was made possible because of a partnership between Yukon Energy and its parent company Yukon Development Corporation. There is also a two-year scholarship worth $4000 for one Francophone student. The same qualifying rules apply as for the general scholarship, with the exception that the recipient must have French as their first language. Yukon Energy is partnering with the Yukon government’s Bureau of French Language Services and the Francophone School Board to offer this scholarship. A scholarship of up to $1,000 will be awarded to a member of the First Nation of Nacho Nyak Dun, and a second scholarship of up to $1,000 will go to a member of the Tr’ondek Hwech’in First Nation. In these cases, the recipients must be studying at a post-secondary institute for a certificate, diploma or an undergraduate degree. These two scholarships were established as part of the benefits agreement with the two First Nations when the decision was made to build a power transmission system from Mayo to Dawson City. Whitehorse resident Ben Craigen is one of the students who is currently benefiting from a Yukon Energy scholarship. “This scholarship has been extremely helpful financially,” Craigen said. “I applaud the efforts of Yukon Energy in providing such a wonderful scholarship opportunity to hard working Yukon students.” Application forms are available from local schools, admission offices, guidance counselors, the First Nation offices in Mayo and Dawson City, or from Yukon Energy or Yukon Development Corporation. They are also available on Yukon Energy's Web site by going to our scholarships page. The deadline to apply is June 30.  -30- Contact:Janet PattersonCommunications, Yukon Energy Corporation(867) 393-5333janet.patterson@yec.yk.ca  

Media Releases
Oct 07, 2005  Comment

Yukon Energy Produces New Learning Materials for Schools

Yukon teachers and students now have some new learning materials to use in the classroom, thanks to Yukon Energy.  The electrical company has produced a web-based brochure and a DVD, aimed at elementary school aged children. The brochure, with colourful illustrations and photos, explains in simple terms how electricity is created and how hydro plants work to produce power. The DVD, produced in partnership with the Kwanlin Dun First Nation and the Department of Fisheries and Oceans, uses photos and narration to detail the life cycle of the chinook salmon. The DVD is available in English, and will soon be available in French and Southern Tutchone.  “At Yukon Energy, public education is an important component of what we do,” company spokesperson Janet Patterson said. “We have been encouraging classrooms to visit our Whitehorse hydro plant and fishladder for some time. This new material will provide students with a broader understanding of the kinds of things they’re exposed to when coming to our facilities.” “The Department of Education is pleased to have access to these new educational materials from Yukon Energy,” Minister of Education John Edzerza said. “It’s important to make what’s taught in the classroom both culturally and environmentally relevant to students—we appreciate Kwanlin Dun’s participation in the project.” The web-based brochure can be found at www.yukonenergy.ca/community/education. Teachers interested in using the DVD in their classrooms can contact Yukon Energy. -30- Contact:Janet Patterson                                                            Supervisor, CommunicationsYukon Energy Corporation(867) 393-5333                                                             janet.patterson@yec.yk.ca

Media Releases
Oct 20, 2005  Comment

Yukon Utilities Board Renders Decision on Yukon Energy Application

The Yukon Utilities Board has handed down its Order regarding Yukon Energy’s application for approval of 2005 revenue requirements. Yukon Energy officials are now reviewing the document to determine its implications. “While we need some time before we can comment in any detail on the Board Order, it’s obvious that the Utilities Board has dealt comprehensively with all the issues brought forward,” Yukon Energy President David Morrison said. “In the interests of transparency and accountability, it was important for us to get back before the Board for the first comprehensive review of Yukon Energy since 1996,” Morrison added. “Yukon Energy welcomed this process and we are pleased that the Utilities Board has now rendered its decision. I want to thank board members for all their hard work regarding this application.” Yukon Energy filed an application for approval of its 2005 revenue requirements last December, including confirmation of all existing firm rates. Oral hearings took place in April. The Board Order confirms and sets as permanent all current firm rates for residential and commercial customers. -30- Contact:Janet Patterson                                                 Communications Supervisor                                          Yukon Energy Corporation                                          (867) 393-5333                                                           janet.patterson@yec.yk.ca

Media Releases
Jan 29, 2006  Comment

Yukoners Urged to Conserve Electricity in Light of Week-end Power Failure

(Whitehorse) – Yukon Energy is continuing to work into the night to restore full service on its Whitehorse-Aishihik-Faro grid. A major outage on the grid at about 1:30 this afternoon resulted in a black-out throughout the system. People from south of Whitehorse to Haines Junction and north to Carmacks and Faro were without power for several hours. While most places now have their power restored, there are still a few pockets that are without power this evening. “This is what’s known as a catastrophic outage,” Yukon Energy spokesperson Janet Patterson said. “It began when one of our Aishihik generators when down. That put too much of a strain on the other operating generators, causing a cascade effect as one by one, they shut down as well. We were left with no hydro generation at all. This is a rare occurrence that tends to only happen every 10 or 15 years.” Because of the complexity of the outage, it took Yukon Energy several hours to bring some of its Whitehorse hydro units back on line. It also fired up its seven diesel generators. Yukon Energy is still working to get the Aishihik hydro generators operating again. In the meantime, Patterson urges customers to conserve electricity as much as possible during the peak morning and evening hours. She warns that if there is too much of a power demand, Yukon Energy will have to look at having rotating power outages throughout the area served by the power grid.       -30- Contact:Janet Patterson                                                             Supervisor, CommunicationsYukon Energy Corporation(867) 393-5333                                                              janet.patterson@yec.yk.ca    

Media Releases
Jan 30, 2006  Comment

Yukon Energy’s Aishihik Generators to be Back On-line Tomorrow

(Whitehorse) – Yukon Energy expects to have both of its Aishihik generators working on a limited basis by sometime tomorrow. In fact one of the generators is already supplying power to Haines Junction. The two units shut down on Sunday afternoon, causing an outage throughout the Whitehorse-Aishihik-Faro power grid. People from south of Whitehorse to Haines Junction and north to Faro and Ross River were without power for several hours while Yukon Energy worked to restore power using alternate hydro and back-up diesel generators. “We believe we have found the cause of the outage,” Yukon Energy spokesperson Janet Patterson said. “One of the cables failed that runs from the two Aishihik generators to a transformer. We are now working on getting a replacement cable.”  Even without a new cable, Yukon Energy has been able to supply electricity to Haines Junction from one of the Aishihik units. The second unit should be running, at least on a limited basis, by tomorrow afternoon. Both units will be fully restored once a new cable can be shipped to the Yukon from suppliers in Southern Canada. -30- Contact:Janet Patterson                                                             Supervisor, CommunicationsYukon Energy Corporation(867) 393-5333                                                              janet.patterson@yec.yk.ca    

Media Releases
Apr 18, 2006  Comment

Yukon Energy to Provide Scholarships to Local Students

Once again this year, Yukon Energy will award a number of scholarships to Yukoners studying at post-secondary institutions. “These awards are one way of showing our commitment to the people and the communities we serve,” Yukon Energy spokesperson Janet Patterson said. “By providing financial assistance to promising post-secondary students, we're doing what we can to help build a stronger, better-educated workforce and to reinvest in our young people.” The awards will be broken down into two categories. In the general category, two students will receive $4,000 each over two years. To be eligible, students must be studying full-time at a post-secondary school in Canada or Alaska for a diploma or undergraduate degree. They must be pursuing studies in the sciences, engineering, technologies, business administration, commerce or economics. Preference will be given to those studying sciences or engineering. This scholarship was made possible because of a partnership between Yukon Energy and its parent company Yukon Development Corporation. Annual scholarships totaling $3,000 to beneficiaries of the First Nation of Ncho Nyak Dun and the Tr’ondëk Hwëch’in First Nation will be awarded.  An eligible student may receive up to $1,000 over a school year.  In these cases, the recipients must be studying at a post-secondary institute for a certificate, diploma or an undergraduate degree. These two scholarships were established as part of the benefits agreement with the two First Nations when the decision was made to build a power transmission system from Mayo to DawsonCity. “I want to thank Yukon Energy for rewarding local students for their continuous efforts,” 2005 scholarship recipient Shawn Sederberg said. “The support from home is encouraging and the extra money really helps out with rent, tuition and books.” Application forms and eligibility criteria are available from local schools, admission offices, guidance counselors and the First Nation offices in Mayo and DawsonCity. The deadline to apply is June 30.  -30-  Contact:Janet PattersonCommunications, Yukon Energy Corporation(867) 393-5333janet.patterson@yec.yk.ca

Media Releases
May 25, 2006  Comment

Yukon Energy/First Nations Sign Carmacks-Stewart MOU

Yukon Energy and three Yukon First Nations have signed a Memorandum of Understanding (MOU) regarding the proposed Carmacks to Stewart Transmission project. The MOU signed by Yukon Energy, the First Nation of Nacho Nyak Dun, the Selkirk First Nation and the Little Salmon/Carmacks First Nation, lays the ground rules for the parties to work together towards making this initiative a reality. If the project goes ahead, it will see the development of a Carmacks to Stewart line to connect the Whitehorse/Aishihik/Faro and Mayo/Dawson power grids. The current proposal includes a new 138 kV transmission line that would start from a new substation in Carmacks, proceed generally along the Klondike Highway to a new substation at Pelly Crossing (thus providing hydro power to Pelly), and then northwards to connect to the existing Stewart Crossing substation. Yukon Energy also proposes to build a lower voltage spur line connecting the main power line to the Minto Explorations Ltd. copper-gold mining project. It’s proposed that a second spur line be built to the Western Copper Corporation copper mining project, should that mine proceed. “No decisions have been made at this time to proceed with this project, nor has the precise transmission line route been established,” Yukon Energy President David Morrison said. “However this MOU is a big step in the process, and Yukon Energy is looking forward to continuing to work closely with the Northern Tutchone First Nations on this initiative.” Before committing to build the line, Yukon Energy would ask the Yukon Utilities Board to review the project, would seek all necessary environmental permits and approvals, and would conclude arrangements with major mining customers and the Yukon government to ensure that Yukon ratepayers are protected against adverse rate impacts. -30- Contact:Janet PattersonCommunications, Yukon Energy Corporation(867) 393-5333janet.patterson@yec.yk.ca  

Media Releases
Jun 13, 2006  Comment

Yukon Energy Outlines Plan for Meeting Future Power Needs

Yukon Energy has filed a 20-year Resource Plan with the Yukon Utilities Board. The plan addresses the Yukon’s major electrical generation and transmission needs from 2006 to 2025. “This plan will guide us in making sound strategic and long-term decisions regarding our assets and infrastructure,” Yukon Energy President David Morrison said. “It addresses the capacity and energy needs of Yukoners, particularly those supplied on the territory’s Whitehorse Aishihik Faro grid and the Mayo Dawson grid.” The Resource Plan provides background information on the Yukon’s power systems and gives an overview of what Yukon Energy expects its near-term and longer-term requirements will be, taking into account a number of industrial development scenarios. It also sets out some new capacity planning criteria recently adopted by Yukon Energy to better protect customers from outages.  Four near term projects are proposed in the Resource Plan. These projects include installing a third hydro turbine at Aishihik, building a transmission line from Carmacks to Stewart to connect Yukon Energy’s two power grids, extending the lives of three diesel units at the Whitehorse Rapids Generating Station, and applying for an amendment to the Whitehorse Rapids water license that would allow the energy company to hold back water in Marsh Lake during the fall. That water would then be used to generate added firm power during the coldest months of winter. The Resource Plan also proposes activities to enable Yukon Energy to start construction on other projects before 2016 if opportunities arise, to meet the needs of potential new industrial customers, including various potential mines and the Alaska Highway pipeline project. The Resource Plan identifies hydro and coal energy supply options that offer substantial opportunities to produce power over the long term at a cost lower than diesel generation. “No final decision has been made to implement any of these proposed projects,” Morrison said. “We are first seeking input from Yukon Utilities Board and from Yukoners. Prior to the Utilities Board hearing, public meetings will take place to allow individuals and groups to participate in a review of our Resource Plan.” Locations and times of the public meetings will very shortly be advertised in the local media. The Yukon Utilities Board will determine when it will hold a public hearing regarding the Resource Plan.  -30- Contact:Janet PattersonCommunications, Yukon Energy Corporation(867) 393-5333janet.patterson@yec.yk.ca Backgrounder Yukon Energy has filed a 20-year Resource Plan submission with the Yukon Utilities Board (YUB) that addresses our major electrical generation and transmission needs from 2006 to 2025. The last time we submitted a Resource Plan to the YUB was in 1992. The Resource Plan provides background information on the Yukon’s power systems and gives an overview of what we expect our near-term and longer-term requirements will be, taking into account a number of industrial development scenarios as well as new capacity criteria recently adopted by Yukon Energy to better protect customers from outages.  No final decision has been made to implement any of the projects proposed in this plan. We are first seeking review by the Yukon Utilities Board, and input from Yukoners through a series of public meetings. New Capacity Planning CriteriaYukon Energy has adopted new capacity planning criteria to better protect customers from outages. The criteria is based on the approach used by other Canadian utilities today. It requires that we plan our grid systems so that on average we would expect no more than two hours of system outages per year as a result of the amount of generation and related transmission we have installed. It also ensures that even if we lose our system’s single largest winter generating or transmission source, we can continue to provide power to residential and commercial customers. Near Term RequirementsIn the short term (the next few years) Yukon Energy is proposing four major projects to meet electrical needs on the Whitehorse-Aishihik-Faro grid to 2012. Together, the following four proposed projects will provide over 21 megawatts of firm winter capacity, and be sufficient to meet likely power needs through to 2012; Aishihik Third TurbineThis is a proposal that was initially reviewed by the Yukon Utilities Board in 1992. A third turbine can be installed at the existing Aishihik generation station at a cost of about $7 million to reduce future costly diesel generation. Yukon Energy received environmental and Water Board approvals for this project under our new Aishihik Water License. If this project proceeds, we expect the turbine to go into production between late 2009 and 2012, depending on electrical needs and what other initiatives are put in place. Marsh Lake Fall/Winter Storage License RevisionThis proposed project would see an amendment to our Whitehorse Rapids water license by August 2007 that would allow us to hold back up to an additional foot of water in Marsh Lake during the fall (from August 15 to the end of September) in non-flood years. That water would then be used to increase the Whitehorse Rapids hydro facility winter power by 1.6 megawatts. At a capital cost not exceeding $1 million, this project would have no effect on summertime water levels during non-drought years. During flood years, there would also be no change to operations in August and September until after the high water levels have subsided.  During drought years, we would alleviate summer drought conditions to ensure the lake reached its regulated full supply capacity level each year. Carmacks-Stewart Transmission ProjectThis project would see a transmission line running from Carmacks to Stewart Crossing, connecting Yukon Energy’s two power grids. The project will encourage economic development along the corridor and enhance overall system reliability and flexibility. It will enable the Minto mine, the proposed Carmacks Copper mine and the community of Pelly Crossing to have access to hydro power and not need to rely on local diesel generation. The line is forecast to provide the Whitehorse-Aishihik-Faro grid with an additional 5.6 megawatts of firm winter capacity in 2012 at a cost in 2005 dollars of $31.2 million. If the line is built, we are currently planning for it to be in service by mid to late 2008. This project will only go ahead after meaningful consultation occurs with First Nations, review by the Yukon Utilities Board is completed, and all environmental permits are obtained. As well, this project will only proceed if Yukon government infrastructure funding ensures no adverse impact on ratepayers. Diesel Units Life Extension or ReplacementThere are seven diesel generators at our Whitehorse Rapids Generating Station. Our three oldest ones are currently scheduled for retirement between 2007 and 2011. We have confirmed that it is technically feasible to refurbish these units, thus extending their lives by 20 years or more at an expected capital cost of $6.4 million, and work is progressing in a staged manner on this project. Refurbishing these units will provide an added 14 megawatts of winter power on the Whitehorse-Aishihik-Faro grid. Replacing these three units with new diesel units would likely cost, in 2005 dollars, about $6 million more than the estimated refurbishing capital cost.   Replacing these three units by building a second, back-up, transmission line from Aishihik to Whitehorse would also be more expensive than diesel-related improvements. We would only look at this project if new mines are connected to our Whitehorse-Aishihik-Faro grid without the completion of the Carmacks-Stewart line and without the diesel generators’ life extension being completed. Longer-term Industrial Development OpportunitiesThe Resource Plan also proposes activities to enable Yukon Energy to start construction on other projects before 2016 if opportunities arise to meet the needs of potential new industrial customers, including various potential mines and the Alaska Highway pipeline project. Hydro supply options are identified that offer substantial opportunities, if required, to produce power over the long term at a cost lower than diesel generation, provided that specific energy supply resource options are properly matched to expected system loads. New energy-focused power development is contingent, however, on sufficient new industrial power loads materializing. Without new industrial power loads, the plan forecasts that surplus hydro energy generation is likely to remain on the Whitehorse Aishihik Faro grid for at least 15 of the next 20 years.