News & Events

Check this section for Yukon Energy's latest news and coming events.

If you have questions about any of the information posted here, please contact:

Lisa Wiklund
Manager, Community Relations
Yukon Energy Corporation
Phone: (867) 393-5398
Email: Lisa.Wiklund@yec.yk.ca

Regulatory
Mar 19, 2010  Comment

Getting All Our Ducks in a Row

Yukon Energy would like to respond to concerns by the NDP and the Yukon Conservation Society about recent construction contract announcements regarding the Mayo B and Carmacks-Stewart Stage 2 projects. Their fear is that we are moving forward with construction before we have received all the necessary permits and permissions. That is not the case. In terms of the Carmacks-Stewart line, Stage 2 is fully permitted. It has gone through an extensive environmental (YESAB) screening and has also been reviewed by the Yukon Utilities Board (YUB). We have all permits we need to proceed with construction. In fact line clearing on this project began this past November.   On Mayo B, Yukon Energy has consistently informed both YESAB and the YUB that, prior to securing the necessary documents and permits, we would be moving to award a construction contract as well as to purchase key long term equipment.  Yukon Energy has also consistently told both YESAB and the YUB that we cannot start construction, and obviously will not allow the contractor to start construction on Mayo B before all necessary permits are in place.    The Yukon Environmental and Socio-Economic Assessment Board has already issued its draft screening report on the Mayo B project. The report confirms that YESAB is prepared to recommend this project move ahead as long as certain conditions are met. We see no reason why we can't meet those conditions, which are fairly standard requirements for utilities involved in hydro projects.     While we wait for YESAB’s final recommendations and for the conclusion of the Yukon Utilities Board process, there are things we can do to ensure we have everything in order and are ready to go as soon as the permits and permissions are issued. The contract we recently signed with Kiewit allows that company to work with us to prepare for construction, thus ensuring that the Mayo plant can be in operation by our March 31, 2012 federal funding deadline. That work includes things such as planning and engineering, going through the process needed for hiring subcontractors, and setting up the work camp near the Mayo B construction site.   From Yukon Energy’s point of view, it would be irresponsible for us to sit and do nothing until the YUB and the YESAB processes are complete, since that would cause us to miss our project completion deadline of March 31, 2012. By missing the deadline we would not receive the $71 million that has been committed by the federal government. Without Mayo B we would be forced to use more diesel, resulting in higher electricity bills for Yukoners.   We are trying to do right by Yukoners. We think Mayo B is a good project for the territory and we are doing everything we can to ensure it proceeds. 

Regulatory
Mar 25, 2010  Comment

Unravelling the Mysteries of the Utilities Board Process

Yukon Energy and the Yukon Electrical Company Limited have filed a joint Phase II Application to our regulator, the Yukon Utilities Board. Before your eyes glaze over, let us explain what a Phase II Application is and why this might be important to you. You might remember that in 2008 and 2009 each utility went to the Utilities Board separately for what are known as revenue requirement hearings. This process allows the YUB to determine how much money each company needs to operate and what the overall amount is that can be charged to customers for electricity. During the Phase II hearings, the Utilities Board uses the information from the Revenue Requirement Hearings to do a couple of things: It recommends how much of that overall amount is to be allocated to each class of customer (resident, small business, government and industry). In other words, the YUB decides who pays for what amount of the pie. You might not know that while business and industry now pay 100 percent of what it costs to provide them with power, residential customers currently only pay about 70 percent of the true cost of their power. They are subsidized by the government, which pays 130 percent of the cost. It recommends how the rates within each class should be designed. For example, the Utilities Board could determine that people who use under a certain amount of electricity per month should get a reduction on their bill while those using a lot of electricity each month should pay a higher rate. That already happens to a certain extent, but Yukon Energy and Yukon Electrical Company Ltd. are asking that there be even more incentives for people to conserve electricity. The Phase II hearing will also deal with proposed changes to the terms under which the utilities provide service to customers. This covers everything from rights of the utility to access land (such as when a linesperson has to go onto private property to access transmission lines) to the rights of a customer to have their meter tested, as well as the level of service fees. If you want to know more, the entire Phase II hearing application can be found on our web site. As always, if you have questions, please send them our way and we will do our best to answer them.        

Reliability
Apr 08, 2010  Comment

The Power of Time

If you live in the Southern or Central Yukon, you may have noticed some of your clocks losing time over the past several days. The cause stems from a malfunctioning control clock we use here at Yukon Energy to help us regulate the amount of power we generate.  We synchronize the time on a sophisticated electric wall clock with a dead-accurate satellite signal as a means of ensuring the correct amount of power is being generated at any given time. When the time on our electric clock drifts more than 10 seconds in either direction, our operations know there is either more power being generated than is needed, or there isn’t enough power being produced. Either way, the operator will adjust the amount of power production to bring the electric clock back in line with satellite (GPS) time.   In this particular case, our control centre’s wall clock was running faster than the satellite clock, so staff reduced generation as per normal practice. What we didn’t know was that there was a problem with the electric clock. When generation was reduced, that caused all AC clocks (clocks plugged into the wall) to lose time.   The change happened quite gradually so it took a few days before we knew there was an issue with our wall clock.   The clock we use is a sophisticated piece of equipment. This is the first time it has failed since we started using it in 1998. We have ordered another clock and we hope to have it installed within a couple of weeks. In the meantime we are relying on an older clock to regulate power production. The clock that malfunctioned will be repaired and will run in parallel with the new one as a back-up system, hopefully ensuring we don't have this issue again.

News
Jun 04, 2010  Comment

Construction Starts on Mayo B Project

Yukon Energy received some good news this week. We have received all the permits necessary to start groundwork on the Mayo B project, and construction will begin later today or tomorrow. Initial work will include clearing and grubbing (removal of stumps, roots and shrubs) of the area where the penstock will be located. The penstock is the large underground pipe that will carry water to the hydro plant. Last month Yukon Energy received a favourable response to the project from both the Yukon Utilities Board and the Yukon Environmental and Socio-economic Assessment Board (YESAB). However we needed some permits and final approvals before moving ahead with construction. Those came yesterday and today in the form of an energy project certificate, a land use permit, and decision documents from the Yukon and federal governments accepting YESAB's recommendations. Mayo B will increase the ability to generate clean power from five megawatts to approximately 15 megawatts without the need for a new dam. The project will offset greenhouse gas emissions by approximately 25,000 tonnes a year. It is also expected to create job opportunities for approximately 150 people over the next two years, most of whom will be Yukoners. Peter Kiewit Sons Co., the construction contractor, has set up a hiring office in Mayo and is working with the First Nation of Na-cho Nyak Dun and the community of Mayo to ensure local employment and business opportunities during construction. Mayo B is being made affordable due to a $ 53.35 million contribution from the Federal government’s Green Infrastructure Fund as well as $30.15 million from the Yukon Development Corporation and the Yukon government. The other $36.5 million will be paid for by electrical customers. However because the cost will be spread over the lifetime of the project (50+ years) there will not be a rate increase as a result of the Mayo B project.

News
Jun 10, 2010  Comment

News From the Fishladder

Yukon Energy's Whitehorse Rapids Fishladder has opened for the summer season. It's a great place to bring young and old alike. Here are some of the things you'll see if you come for a visit: The underwater fish cameras have been re-activated. The cameras are located at the base of the fishladder and allow you to view the fish in real time. Right now you'll see various types of freshwater fish including grayling and lake trout. In early August the Chinook salmon start to arrive. You can check out our fish cam on our web site.   Those of you who follow this blog might remember that last summer, we unveiled a large public art piece entitled "One Fish, Two Fish". It commemorates the 50th anniversary of the fishladder and shows 55 Chinook salmon travelling up the Yukon River. Each salmon was painted and decorated by Yukon individuals or groups. We had so much positive feedback and interest in the project that we decided to have a Part Two created. This time it's day cares and schools that were invited to decorate the fish. The installation will be open to the public in late June.   We are once again this year offering family season's passes to the fishladder. Normally we request a $3 donation per person for each visit. This family pass allows unlimited visits to the ladder by the entire family for just $10. Since there's so much going on at the fishladder, one visit is never enough, so this pass is very good value. For more information about the fishladder, visit our web site or call 867.633.5965.

Media Releases
Apr 30, 2010  Comment

Yukon Energy and Na-cho Nyak Dun Sign Major Project Agreement

Na-cho Nyak Dun First Nation and Yukon Energy have signed a Project Agreement for the Mayo hydro enhancement project (Mayo B). The agreement was signed yesterday in Mayo. It represents the mutual and beneficial interests shared by YukonEnergy and the First Nation of Na-cho Nyak Dun and the importance of this project for Yukon’s future energy needs. “The signing of this agreement is the first step in our First Nation receiving revenues from a utility for many years into the future and it gives us the opportunity to invest in the ownership of the new hydro electric generating facility,” Chief Simon Mervin said. “The Agreement will, in turn, provide a long-term source of income for our nation and there will be employment and contracting opportunities,” Councillor Mary McMahon explained. “Yukon Energy believes this agreement demonstrates our interest in working with The Na-cho Nyak Dun to ensure local benefits and it enables the First Nation to invest in being a part of building a clean energy future for Yukon,” said David Morrison, President and CEO of Yukon Energy. Along with an investment opportunity, the Na-cho Nyak Dun has an opportunity for substantial economic benefits through sub-contracts and employment opportunities. In addition to the Project Agreement with Na-cho Nyak Dun, Yukon Energy recently signed a construction contract with Peter Kiewit and Sons Ltd. (Kiewit) to build the Mayo B project, which includes the building of a new powerhouse and water conveyance. Kiewit has hired a Na-cho Nyak Dun liaison person to coordinate the hiring of about 120 people. Construction of the Mayo B project will not begin until the Yukon Environmental Social Economic Board process is complete and Yukon Energy has received all of the permits necessary for construction. The Mayo B project is funded in part by Federal government’s Green Infrastructure Fund and a financial commitment from the Yukon government and Yukon Development Corporation. The Mayo B power house brings power generation on site to 15 megawatts without the need for a new dam. -30- For more information contact: Janet Patterson                                                          Communications, Yukon Energy Corporation              (867) 393-5333                                                          janet.patterson@yec.yk.ca    Anne Leckie Executive Director First Nation of Na-cho Nyak Dun (867) 996-2265

Media Releases
Jun 04, 2010  Comment

Permits in Hand; Mayo B Construction Set to Begin

Yukon Energy has received all the permits necessary to start groundwork on the Mayo B project, and construction will begin later today or tomorrow. Initial work will include clearing and grubbing (removal of stumps, roots and shrubs) of the area where the penstock will be located. Last month Yukon Energy received a favourable response to the project from both the Yukon Utilities Board and the Yukon Environmental and Socio-economic Assessment Board (YESAB). However the energy corporation needed some permits and final approvals before moving ahead with construction. Those came yesterday and today in the form of an energy project certificate, a land use permit, and decision documents from the Yukon and federal governments accepting YESAB's recommendations. “We are extremely pleased to have these final hurdles behind us,” Yukon Energy President David Morrison said. “It’s taken a huge amount of time and effort by a great many people to reach this stage and I would like to thank everyone who has worked to advance this project.” Mayo B will increase the ability to generate clean power from five megawatts to approximately 15 megawatts without the need for a new dam. The project will offset greenhouse gas emissions by approximately 25,000 tonnes a year. “It’s our job to provide Yukoners with enough clean, affordable and reliable electricity to keep the lights on and keep businesses thriving,” Morrison added. “Mayo B fits that mandate. It enhances our existing hydro infrastructure, supplies additional clean energy and has a small environmental footprint.” The project will create job opportunities for approximately 150 people over the next two years, most of whom will be Yukoners. Peter Kiewit Sons Co., the construction contractor, has set up a hiring office in Mayo and is working with the First Nation of Na-cho Nyak Dun and the community of Mayo to ensure local employment and business opportunities during construction. While land-based construction of Mayo B is starting now, the water-based work won’t take place until the summer of 2011. Mayo B is expected to be completed no later than March 2012. Mayo B is being made affordable due to a $ 53.35 million contribution from the Federal government’s Green Infrastructure Fund as well as $30.15 million from the Yukon Development Corporation and the Yukon government. The other $36.5 million will be paid for by electrical customers. However because the cost will be spread over the lifetime of the project (50+ years) there will not be a rate increase as a result of the Mayo B project. Contact: Janet Patterson Supervisor, Communications Yukon Energy Corporation (867) 393-5333 janet.patterson@yec.yk.ca